Upgrade works to Clayton Hall

 03 January 2019

Clayton Hall - Main Hall

Work to upgrade the Clayton Hall ceiling and improve lighting at the hall will start from Monday 14 January, 2019.

The improvements include joinery, plastering and painting the the main hall and meeting room 2 ceilings. The main hall works are expected to be completed by Friday 25 January 2019 with the meeting room 2 works due to be completed by Friday 15 February 2019.

The main hall will be closed for two weeks during the works with meeting room 2 closed for four weeks.

Any queries, please contact Monash Council on 9518 3555.

 

 

 

Subscribe to page updates

Fields marked as 'Required' must be completed.