Brandon Park Reserve Pavilion
- Project typePavilion
- Project value$4.6 million
- Project scheduleAugust 2025 - May 2026
- Contractor nameShape
- Completion date31 May 2026
We are building a new modern, modular pavilion that will make better use of the reserve's space for players, teams, visitors and community members.
The pavilion development is supported by the Victorian Government's Community Sport and Recreation Projects program.
Project milestones
August 2025 - January 2026: Constructing and installing the pavilion at the northern car park next to the playground.
January - February 2026: Demolishing the existing pavilion once the new one is open
January - May 2026: Constructing a new car park
Follow updates: Brandon Park Reserve Pavilion | Shape Monash
About the project
The new facility will support more community participation in local sport by including:
- Four change rooms
- Social rooms and kitchen
- Umpires and first aid room
- Storage area
- Tiered seating
- Public toilet
Impacts to local residents and visitors
The northern car park will be closed and fenced off as the construction zone for the new pavilion, with signs in place to help alert drivers. The southern car park will remain open for use.
Aerial view of car park closure
There may be some days of higher activity. Please follow all on-site signage.
The pathway connecting the current pavilion and playground will be closed. Temporary pedestrian access and clear signage will ensure safe navigation for visitors and community members.
Location
8-26 Charles Street, Mount Waverley 3149 View Map
-37.8724841,145.1344301
8-26 Charles Street ,
Mount Waverley 3149
8-26 Charles Street ,
Mount Waverley 3149
Brandon Park Reserve Pavilion