Construction Management Plans

1. Overview

As a builder or developer, you are responsible for managing all work you carry out within the municipality, including excavation, demolition and construction activities. This includes work undertaken by your subcontractors.

A Construction Management Plan (CMP) outlines how construction activities will be managed to minimise impacts on the surrounding community, road users and Council assets.  

A CMP is required for large or complex developments. If required, you will need to submit a CMP application to be checked and approved by Council’s Engineering Department before construction works begin.

Important: You must submit your Construction Management Plan online.

2. Who needs a CMP

You must submit a CMP if: 

  • your Planning Permit requires one
  • Council has requested one in writing.

Important: As the builder or developer, you are responsible for preparing and submitting the CMP, including managing subcontractor activities.

3. What to include in your CMP

Your CMP must cover: 

  • public safety, site security and amenity 
  • the scope and duration of each construction stage, including operating hours 
  • noise and vibration control 
  • air quality and dust management 
  • stormwater and sediment control 
  • tree protection zones 
  • excavation details 
  • waste minimisation 
  • on-site storage of materials and equipment 
  • use of cranes, concrete pumps or site sheds.

Your CMP must also include:

  • construction vehicle types, sizes, frequency and routes (with swept paths provided for the largest vehicle) 
  • worker access and parking arrangements/mitigation 
  • traffic and pedestrian management measures 
  • road closures or works zones with traffic control plans.

Important: To avoid delays, ensure all information is complete and accurate before submitting your application. Changes to an approved CMP will require a new application.

4. Submit your CMP

You must lodge your Construction Management Plan Application online and include all required supporting documents.

Apply online

Important: Construction works cannot commence until the CMP has been approved. Failure to comply may lead to fines or a stop-work order. 

5. How your CMP is assessed

All works must comply with relevant legislation, including Council’s Community Safety and Amenity Local Law.

Council assesses CMPs to ensure:

  • public safety
  • amenity protection
  • traffic management
  • asset protection and
  • environmental responsibility.

Other permits you may need

As part of your project, you may also require the following permits or approvals: 

Important: To avoid delays, we recommend submitting any required applications for approval at the same time as the CMP. 

6. What happens next

Once your application and supporting documents have been received: 

  • You will receive an email confirming that your application has been received and allocated to an officer for assessment
  • We will usually provide an initial response within 20 business days
  • If further information is required, we will contact you at this stage
  • You may be required to amend your CMP before the final assessment
  • The final assessment may take an additional 20 business days.